What should the project manager do?

In a multinational project, stakeholders are in different time zones. The project manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the project sponsor that they know very little about the project.

What should the project manager do?
A . Discuss the issue with all stakeholders and work on a communications management plan to meet all stakeholder requirements.
B . Ensure that the stakeholders who are complaining are present for the next project update meetings.
C . Record the regular project update meeting and share it with all stakeholders after the meeting is completed.
D . Change the meeting time to the working time zones of the stakeholders who are complaining.

Answer: A