What should the project manager do?

A project team member requests a change that will impact the project’s major functionality. A subject matter expert (SME) conducts an impact assessment and determines that this change will affect the project’s timeline.

What should the project manager do?
A . Refer to the change management plan, then, if necessary, review the change request in the change control meeting.
B . Work with the team member and the SME to identify a workaround or alternative that will not impact the timeline.
C . Approve the change, prioritize it within the project, then, if necessary, re-baseline the timeline.
D . Recommend implementing the change in the next phase.

Answer: A