What should the project manager do?

An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion of this key project phase: affected community members begin a four-day protest causing the project to be put on hold.

What should the project manager do?
A . Increase effort on the project.
B . Mitigate the risk.
C . Review the timeline
D . Escalate the issue to the project sponsor

Answer: D