What should the project manager do?

A project manager receives project charier approval for an expansion project Subsequently the government introduces a new regulation with which the expansion project must comply This will significantly impact the project’s schedule and budget

What should the project manager do?
A . Revise the project charter after estimating the impact of the new regulation, and then obtain approval
B . Estimate the impact of the new regulation, and establish a project plan that includes this impact
C . Include the risk of the new regulation in the risk register, and monitor the impact of the risk.
D . Start the project planning phase according to the approved project charter without considering the new regulation.

Answer: A