What should the project manager do?

A company has a history of implementing system integration projects using their-in-house software with a vendor infrastructure A project manager, new to the company, has no prior experience with vendor integration projects

What should the project manager do?
A . Refer to the project statement of work (SOW)
B . Review the project charter.
C . Seek expert judgment
D . Meet with the sponsor.

Answer: C