What should the project manager do?
A large risk to a project is identified and the risk management plan is executed Upon completion of the approved actions.
What should the project manager do?
A . Update the risk management plan
B . Revise the project schedule and the budget
C . Update the lessons learned
D . Identify new risks. and monitor residual risks
Answer: D