What should the project manager do?

A team completes a prototype of a new product utilizing the latest technology. During testing it fails to meet performance specifications

What should the project manager do?
A . Perform a root cause analysis to identify the reason
B . inform the sponsor, and implement corrective actions
C . Renegotiate the performance specifications with the project sponsor
D . Submit a deviation request to the change control board (CCB)

Answer: A