A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users.
What should the project manager do?
A . Ensure that the user guide is detailed and has clear instructions.
B. Ensure that comprehensive documentation is handed over.
C. Ask the project team to provide operational support for 1 year.
D. Ensure that knowledge is transferred to the operations team.
Answer: A
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund