What should the project manager do?

While preparing for project hand-over to the operations team, the project manager discover that an audit report from an early project phase is missing.

What should the project manager do?
A . Update the project documents.
B . Ask the operations teams to accept the project without the audit report.
C . Inform the operations team about the missing audit report
D . Update the project management plan to remove the audit report from the required project documents list.

Answer: A