What should the project manager do?

A project team has finished its first iteration out of six. The iteration’s delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was

underestimated.

What should the project manager do?
A . Update the issue log and escalate it to the project sponsor.
B. Meet with the team to review internal actions to resolve the situation.
C. Ask the technical manager to help the team with the issue.
D. Ask to replace some team members with more experienced ones.

Answer: B