What should the project manager do?
A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.
What should the project manager do?
A . Use the compliance issues to identify coaching and mentoring opportunities.
B. Log the feedback from the compliance gaps in the lessons learned register.
C. Review this with the project sponsor to avoid compliance gaps and issues.
D. Discuss the suggestions with the staff responsible for the compliance issues.
Answer: D