A project is being executed. The project’s life cycle is defined as predictive; however, a major deliverable will be handed over incrementally to the customer. The assigned resources are experienced and reliable and are willing to make decisions that the project manager used to make after each incremental delivery on other projects.
What should the project manager do?
A . Support the decisions of the team and transfer the decision making responsibility to them.
B. Consult the product owner about letting the resources make decisions.
C. Schedule a steering committee meeting and obtain their approval on the request.
D. Inform the team that although this is a hybrid environment, the project manager must still be responsible for making decisions.
Answer: A