What should the project manager do?

A project manager has recently been assigned to a new project. When the project manager first meets the project team, the team tells the project manager that all of the management plans and documents for the project are missing.

What should the project manager do?
A . Ask the stakeholders to develop all of the project artifacts so the project team can continue their scheduled activities.
B. Create the project management plans with the project team and share the documents with the stakeholders.
C. Continue working on scheduled tasks to avoid delaying the project and leave the development of project artifacts for later.
D. Adapt the project management plans and documents from previous executed projects in order to save time.

Answer: B