What should the project manager do?

A project requires the procurement of a large amount of equipment that needs to be on-site before any other activity can begin. The procurement department has a lengthy approval process.

What should the project manager do?
A . Ask the project sponsor to expedite the vendor selection process.
B. Contact the vendor that supplied similar equipment for a previous project.
C. Use the existing equipment and replace it later with the new equipment.
D. Work with the procurement team to find alternative options.

Answer: D