A project with a hard timeline is starting its first iteration out of six. The project team is lacking the necessary skills to execute.
What should the project manager do?
A . Allow the team to proceed as they attempt to meet the timeline.
B. Add a subject matter expert (SME) to the project team.
C. Invite stakeholders to discuss a mitigation plan to finish on time.
D. Fill the skill gap personally to execute the project.
Answer: D