What should the project manager do?

A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?
A . Update the issue log and escalate the problem to the project sponsor.
B. Ask for a project extension to deliver the committed scope.
C. Review the options and possible solutions with the project team.
D. Ask for help to increase the team capacity to deliver on time.

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments