What should the project manager do?
A project team is trying to meet the milestone target dates in order to receive a bonus promised by the project sponsor. Unforeseen challenges and poor communication among the team members resulted in mistakes and delays. Tensions are high, and the sponsor is concerned.
What should the project manager do?
A . Schedule a team-building activity to boost the team’s morale.
B. Discuss with the team how the project objectives can be met.
C. Organize a team meeting to remind the team of the ground rules.
D. Request that the sponsor increase the bonus for high performers.
Answer: A