A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team’s performance as a whole is low, especially in terms of group activities.
What should the project manager do?
A . Negotiate for new team members.
B. Review and update the communications management plan.
C. Review and reassign team assignments.
D. Facilitate communication and team building.
Answer: D