What should the project manager do?
A project manager implements an information system for a financial company. A senior It manager indicates that quality control has not identified any failures and that the new system is ready for end users
What should the project manager do?
A . Transfer the product lo the client
B . Distribute the final project report.
C . Start the Close Project or Phase process
D . Validate the project’s scope and obtain sponsor approval
Answer: D