What should the project manager do?
A vendor communicates that the delivery of a project item will be delayed by two weeks.
What should the project manager do?
A . Conduct a variance analysis.
B . Implement the Perform Integrated Change Control process
C . Review the contract clause for liquidated damages
D . Identify a way to conduct schedule compression.
Answer: C