The project sponsor on an agile project informed the project lead that an executive would like an update on the project’s progress.
What should the project lead do?
A . Provide a link to the project’s shared drive for the executive to search through for any artifacts that are of interest.
B . Invite the executive to the project’s meeting space to determine if the project information radiators meet their needs
C . Reach out to the project management office (PMO) for status report templates and provide project updates in that format
D . Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments
Answer: B