A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.
What should the project lead do?
A . Invite the board member to the next daily standup.
B. Invite the board member to the next sprint retrospective.
C. Invite the board member to a separate demo.
D. Invite the board member to the next sprint review.
Answer: D