What should the program manager do to ensure communications on the component projects are consistent?
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company’s staff
What should the program manager do to ensure communications on the component projects are consistent?
A . Request a more experienced project manager to work on project 6
B. Create a program communications management plan across all component projects
C. Direct all projects to use project A’s communications management plan as a template
D. Rework the communications management plans for all projects to be consistent
Answer: D
Latest RCDDv14.1 Dumps Valid Version with 320 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments