A program manager recognizes that a successful resource being used in project A could also be used in project B.
What should the program manager do first to leverage the utilization of this resource?
A . Assign project A’s resource to project B
B. Reassign the resource to project B after protect A ends
C. Prioritize the resource to optimize their use across both projects A and B
D. Mitigate risk by leveraging other resources in project A
Answer: C