A key stakeholder’s requirement contradicts the organization’s strategic objectives . The program manager meets with the stakeholder, but is unable to reach a compromise on the requirement.
What should the program manager do first?
A . Meet with the program management office to update the benefits management plan
B . Meet with organization’s strategic planning committee to obtain clarification
C . Meet with the program sponsor to address the issue
D . Meet the customer to determine if the stakeholder’s requirement is valid
Answer: C