During Sprint Planning, it is identified that Team C will not have enough work due to the dependencies from Team A and Team B.
What should the Nexus team do with Team C?
A . Assign them the work of documentation, testing and Integration
B. Practice pair-programming so that the members can participate in the development work of Team A and B
C. Assign them the PB items which are on the bottom
D. Release them from the project until there is enough work
Answer: B
Explanation:
In Nexus, it is a real possibility that one of the teams does not have enough work due to dependencies.
Pair Programming is a great practice in this kind of situation.