What should the Development Team do?

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress.

What should the Development Team do?
A . Add the item to the current Sprint and drop an item of equal size.
B . Add the item to the current Sprint without any adjustments.
C . Inform the Product Owner so he/she can work with the CE
E . Add the item to the next Sprint.

Answer: C

Latest PSM I Dumps Valid Version with 197 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
andre.cc
andre.cc
2 years ago

only PO can do it