What should the customer do to minimize the effect of the deletion job?
A customer has a 5 node Isilon cluster. The raw capacity of the cluster is 85% used. On average, the cluster has 4,000 users connected during office hours. The average CPU usage is 65%. The customer needs to delete some data to free up capacity.
What should the customer do to minimize the effect of the deletion job?
A . Delete the data from a client directly connected to the cluster
B . Run the treedelete job with a high impact and high priority during out-of-office hours.
C . Run the treedelete job with a high impact and high priority during office hours.
D . Run the treedelete job with the default impact and priority during out-of-office hours.
Answer: D