A project affects Ihe marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.
What should the business analyst do immediately after the discussion?
A . Schedule time with the process owners.
B . Develop an issues log.
C . Assess the risks for the project.
D . Put the information into a project plan.
Answer: C