What should the agile project lead have done to avoid this situation?

A project with multiple teams recently transitioned from a predictive approach to agile as requested by the product owner. Midway through implementation, a team member noticed there was no technical capability to support the current business requirement; therefore, the project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?
A . Assessed the technical and organizational readiness for the project and identified risks at the beginning of the first iteration
B . Requested the product owner’s approval to add an external expert to define the acceptance criteria
C . Defined a clear acceptance criteria at the initiation phase and continued with the project
D . Increased the communications between the team member and the product owner

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments