Three Development Teams are currently building a single product and pulling work from the same Product Backlog. All three teams have identified that they will need Dan, a database specialist, to work full time in their team for the next several Sprints.
What should Steven, the Scrum Master, do to solve this potential problem?
A . Manage the items in the Sprint Backlogs so that Dan can be utilized evenly for each team.
B . Assign Dan to the team with the most urgent tasks first and then move him to the next team and so on until the required support is completed.
C . Facilitate a discussion with all Development Teams on how they want to deal with this issue, and help them implement their preferred solution.
D . Ask Dan to work with the HR department to recruit and hire additional database specialists. In the meantime, have the Product Owner move items that do not depend on Dan to the top of the Product Backlog.
Answer: C
Explanation:
As a servant/leader, the Scrum Master facilitates conversations through open ended questions in order to help the team members make the best possible decisions according to what is known at the time. He/she does not approve or reject team decisions but ensures the team stays within the boundaries of the Scrum framework.
Latest PSM II Dumps Valid Version with 180 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund