What should project manager to do next to minimize the impact on the project?

A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.

What should project manager to do next to minimize the impact on the project?
A . Schedule a meeting with all stakeholders to extend the project deadline
B . Replace the vendor with a new vendor who can offer the component on time
C . Add an item to the next status review to make stakeholders aware of the vendor issue.
D . Review and update the issue log and determine if any alternative components can be offered

Answer: D