What should be your answer to him?

You are managing a complex portfolio with high risk levels due to emerging technological breakthroughs and a short benefit window to market your product. You know that managing

risk is key to success and you are coaching your team on the same. One of your team members came to you asking about the order of the steps used to perform risk management activities .

What should be your answer to him?
A . Risk Identification, Risk Assessment, Response Planning, Risk Response
B . Risk Planning, Risk Assessment, Risk Response
C . Response Planning, Risk Identification, Risk Assessment, Risk Response
D . Risk Identification, Response Planning, Risk Assessment, Risk Response

Answer: B