One of your company’s junior portfolio managers came to you for advice. He noticed while checking the roadmap that it does not include all the portfolio components .
What should be your advice to him?
A . The roadmap does not include all of the portfolio components, it is used as a high-level timeline
B . The roadmap should include all of the portfolio components in order to correctly depict the different timelines and milestones
C . Whether the roadmap includes all or a part of the portfolio components, is the decision of the portfolio manager
D . Whether the roadmap includes all or a part of the portfolio components, is the decision of the portfolio sponsor
Answer: B