Exam4Training

What should be done?

A Scrum Master is asked to help an Agile Release Train that has struggled through multiple Pls. They just finished the second Iteration in the current Pl and have nothing to show at the System Demo. The ART stakeholders are concerned.

What should be done?
A . Have every team demonstrate their team increment to the stakeholders separately in the team branch
B. Find a vendor that specializes in integrating system increments from multiple teams
C. Stop working on any new functionality and fully integrate and test the system; adjust scope based on what is learned
D. Re-architect the system so that there are no dependencies between the teams; integration is not
required at this time

Answer: C

Explanation:

If ART is struggling to integrate then Stop working on any new functionality and fully integrate and test the system; adjust scope based on what is learned.

Latest SASM Dumps Valid Version with 185 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version