A three-year program using vendor contracts, incorporating related projects, and each with specific stakeholders is coming to an end.
What should be completed first to close all appropriate contracts?
A . Certify contract completion
B. Conduct a procurement audit to review the procurement process
C. Assess all contracts to ensure all agreed conditions are mot
D. Review contract management plan for completeness
Answer: C