During Program Increment (PI) execution, the System Team is unclear about how to test some of the larger Features.
What should a Release Train Engineer do?
A . Allow the problem to reach a critical point knowing that a minor failure is a tech-nique for learning
B. Encourage the System Team and Product Management to meet and collaborate on a solution
C. Escalate the problem to senior management to get the required action
D. Direct Product Management to define the use cases for the Features
Answer: B