What Risk Priority Number (RPN) you would give to it?
You are the risk official in Bluewell Inc. You are supposed to prioritize several risks. A risk has a rating for occurrence, severity, and detection as 4, 5, and 6, respectively.
What Risk Priority Number (RPN) you would give to it?
A . 120
B . 100
C . 15
D . 30
Answer: A
Explanation:
Steps involving in calculating risk priority number are as follows:
– Identify potential failure effects
– Identify potential causes
– Establish links between each identified potential cause
– Identify potential failure modes
– Assess severity, occurrence and detection
– Perform score assessments by using a scale of 1 -10 (low to high rating) to score these assessments.
– Compute the RPN for a particular failure mode as Severity multiplied by occurrence and detection.
RPN = Severity * Occurrence * Detection
Hence,
RPN = 4 * 5 * 6
= 120
Incorrect Answers:
B, C, D: These are not RPN for given values of severity, occurrence, and detection.
Latest CRISC Dumps Valid Version with 933 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund