What Risk Priority Number (RPN) you would give to it?

You are the risk official in Bluewell Inc. You are supposed to prioritize several risks. A risk has a rating for occurrence, severity, and detection as 4, 5, and 6, respectively.

What Risk Priority Number (RPN) you would give to it?
A . 120
B . 100
C . 15
D . 30

Answer: A

Explanation:

Steps involving in calculating risk priority number are as follows:

– Identify potential failure effects

– Identify potential causes

– Establish links between each identified potential cause

– Identify potential failure modes

– Assess severity, occurrence and detection

– Perform score assessments by using a scale of 1 -10 (low to high rating) to score these assessments.

– Compute the RPN for a particular failure mode as Severity multiplied by occurrence and detection.

RPN = Severity * Occurrence * Detection

Hence,

RPN = 4 * 5 * 6

= 120

Incorrect Answers:

B, C, D: These are not RPN for given values of severity, occurrence, and detection.

Latest CRISC Dumps Valid Version with 933 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments