What recommendation should the risk manager make to the project manager?

The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.

What recommendation should the risk manager make to the project manager?
A . Add more float to the key activity
B. Add more contingency to the project
C. Review the plans for the key activity
D. Increase the budget for the key activity

Answer: C

Explanation:

The risk manager should recommend that the project manager review the plans for the key activity, as this will help identify potential issues and opportunities to improve the activity’s performance and reduce its impact on the critical path.