What project scenario does this describe?

A project’s budgeted value of work completed is less than the authorized budget for planned work.

What project scenario does this describe?
A . Project activity is behind schedule.
B . The project is on schedule.
C . The project is ahead of schedule
D . The earned value (EV) of the project is greater than the planned value (PV)

Answer: D