What project scenario does this describe?
A project’s budgeted value of work completed is less than the authorized budget for planned work.
What project scenario does this describe?
A . Project activity is behind schedule.
B . The project is on schedule.
C . The project is ahead of schedule
D . The earned value (EV) of the project is greater than the planned value (PV)
Answer: D