What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A . Configuration Item Record
B . Quality Register
C . Highlight Report
D . Checkpoint Report

Answer: C

Explanation:

The Highlight Report in PRINCE2 is used by the Project Manager to review the performance of a Work Package against its cost tolerance, among other factors. This report provides the Project Board with a summary of the stage status, and is a key tool for monitoring overall project progress, including financial performance.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources