What product is used to maintain a record of those who have an interest in the project and their information requirements?

What product is used to maintain a record of those who have an interest in the project and their information requirements?
A . Project Plan
B . Communication Management Strategy
C . Project Brief
D . Project Product Description

Answer: B

Explanation:

The Communication Management Strategy is used in PRINCE2 to maintain a record of stakeholders who have an interest in the project and their information requirements. This document outlines how and when stakeholders will be kept informed about the project’s progress and any issues that may arise.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources