What product defines the reporting requirements between the Project Manager and Team Manager?

What product defines the reporting requirements between the Project Manager and Team Manager?
A . Project Brief
B . Product Description
C . Team Plan
D . Work Package

Answer: D

Explanation:

The Work Package is the product that defines the reporting requirements between the Project Manager and the Team Manager. It describes the work, specifies the product’s description, and sets out the reporting requirements among other information, ensuring that both managers have clear guidelines on communications regarding the package’s delivery.

Reference: PRINCE2® Foundation official documentation and study materials.