What product defines the reporting requirements between the Project Manager and Team Manager?
What product defines the reporting requirements between the Project Manager and Team Manager?
A . Project Brief
B . Product Description
C . Team Plan
D . Work Package
Answer: D
Explanation:
The Work Package is the product that defines the reporting requirements between the Project Manager and the Team Manager. It describes the work, specifies the product’s description, and sets out the reporting requirements among other information, ensuring that both managers have clear guidelines on communications regarding the package’s delivery.
Reference: PRINCE2® Foundation official documentation and study materials.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments