What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?
What process is used by the Project Manager to maintain focus on delivery of a stage’s products within agreed tolerances?
A . Directing a Project
B . Controlling a Stage
C . Managing a Stage Boundary
D . Managing Product Delivery
Answer: B
Explanation:
The Controlling a Stage process is used by the Project Manager to maintain focus on the delivery of the stage’s products within the agreed tolerances. This involves assigning work, monitoring such work, managing issues and risks, and ensuring that the stage remains on track in terms of time, cost, quality, scope, risk, and benefit performance.
Reference: PRINCE2® Foundation official documentation and study materials.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments