What process ensures focus on the delivery of a stage’s products and avoids uncontrolled change?
A . Directing a Project
B . Managing a Stage Boundary
C . Controlling a Stage
D . Starting up a Project
Answer: C
Explanation:
The Controlling a Stage process in PRINCE2 ensures focus on the delivery of a stage’s products while managing and controlling any potential deviations or issues. This process helps in avoiding uncontrolled changes and maintains the project’s focus on its objectives by providing regular monitoring and control.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources