An engineer wants to create a 4-node cluster after rack and stack.
What port must they use to start the installation?
A . COM
B . FE
C . BE
D . iDRAC
Answer: D
Explanation:
When an engineer wants to create a 4-node cluster after rack and stack, they must use the iDRAC (Integrated Dell Remote Access Controller) port to start the installation.
Understanding iDRAC:
Remote Management:
iDRAC provides out-of-band management capabilities, allowing administrators to manage and
monitor nodes remotely.
Virtual Console Access:
Offers a virtual console for accessing the node’s BIOS and performing installations.
Initial Cluster Setup with iDRAC:
Accessing the Node:
Connect to each node’s iDRAC interface using its IP address.
Starting the Installation:
Use the iDRAC virtual console to interact with the node as if you were physically present.
Benefits:
No need for physical access to the COM port or direct console connections.
Allows for remote configuration and reduces the time required for setup.
Why iDRAC is Used Over Other Ports:
COM Port:
The COM (serial) port can be used for initial setup, but it requires physical access and serial cables.
Less convenient compared to iDRAC’s remote capabilities.
FE (Front-End) and BE (Back-End) Ports:
FE and BE ports are used for data network connections, not for initial setup or management.
The initial configuration cannot be performed through these ports.
Procedure for Using iDRAC:
Step 1: Connect to iDRAC
Ensure that iDRAC network interfaces are connected and configured with IP addresses.
Access iDRAC via a web browser using the IP address.
Step 2: Launch Virtual Console
Log in to the iDRAC interface.
Launch the virtual console to access the node’s system interface.
Step 3: Perform Initial Configuration
Use the virtual console to run the OneFS installation wizard. Configure cluster settings, networking, and other parameters. Dell PowerScale Best Practices: Using iDRAC for Installation:
Recommended for its convenience and efficiency.
Allows for consistent setup procedures across multiple nodes.
Network Preparation:
Ensure iDRAC interfaces are properly connected to the management network.
Verify network settings to allow access from the engineer’s workstation.
Dell PowerScale
Reference: Dell EMC PowerScale OneFS Installation Guide:
Provides detailed steps on installing OneFS using iDRAC.
Dell EMC PowerScale Networking Guide:
Discusses management network configurations, including iDRAC setup.
Dell EMC iDRAC User’s Guide:
Offers comprehensive information on using iDRAC features.
Knowledge Base Articles:
Article ID 000125678: "Initial Cluster Configuration Using iDRAC"
Article ID 000125679: "Best Practices for Remote Installation on PowerScale Nodes"
Latest D-PSC-MN-01 Dumps Valid Version with 139 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund