What plan should be reviewed to eliminate these differences?

An organization has contracts with an external supplier to support a critical part of a project Senior management and the project ream have differences about what deliverables the external supplier should provide.

What plan should be reviewed to eliminate these differences?
A . Delivery management plan
B . Scope management plan
C . Contract management plan
D . Procurement management plan

Answer: D