What operation was in progress when the power button was blinking green?
An administrator is asked to install and power-on a new MX740c sled in an MX7000 chassis. The administrator inserts the sled and presses the power button. They notice that the power button LED is blinking green. After a short time power button turns to solid green and the server finally turns on.
What operation was in progress when the power button was blinking green?
A . iDRAC was booting
B . Lifecycle Controller update was in progress
C . Lifecycle Controller was taking firmware inventory
D . iDRAC was updating firmware
Answer: A