What must be set up on the corresponding Prefect custom form so the Required Delivery Dale and the original number of Allowable Days display on the project?

A request form has a calculated field Allowable Days that calculates the number of days between the request Entry Date and the custom field Required Delivery Date.

What must be set up on the corresponding Prefect custom form so the Required Delivery Dale and the original number of Allowable Days display on the project?
A . Add both the Allowable Days and the Required Delivery Date fields as new text fields.
B . Add both Allowable Days and Required Denver Dale as calculated fields referencing the request object.
C . Add Allowable Days as a calculated field and add Required Delivery Dale as a text field.

Answer: C

Explanation:

In this scenario, the calculated field Allowable Days and the Required Delivery Date need to display on the project.

To achieve this:

Allowable Days: This is a calculated field, so it should be set up as a calculated field in the project custom form, which references the difference between the Request Entry Date and the Required Delivery Date.

Required Delivery Date: This is a static field and should be displayed as a text field to ensure that the original requested delivery date is retained.

Option B is incorrect because both fields do not need to be calculated. The Required Delivery Date is already a static value and doesn’t require calculation.

For more information, refer to the Workfront documentation on setting up calculated fields and text fields in custom forms.