What must be done to complete this task?

Your customer plans to use HPE Primera to boot HPE Synergy compute nodes. They currently have two HPE Virtual Connect SE 100Gb F32 Module for Synergy modules installed in the frame. The customer wants to use FC as a storage access protocol

What must be done to complete this task?
A . Enable FC primary and secondary boot on the modules through the HPE OneView interface
B . FC connectivity on the modules should be enabled through the service console by disabling FCoE.
C . Add FC upgrade licenses in HPE OneView that will enable FC connectivity for the modules
D . Enter both modules into a maintenance mode, then enable FC connectivity through CLI

Answer: B